Risky building assessment and objection

A risky building assessment is primarily commissioned by the owners or their legal representatives, at their own expense, from institutions licensed by the Urban Transformation Presidency. The Presidency or the competent administration may also carry out the assessment of its own motion or request it from the owners within a set period. The assessment is recorded in the declarations section of the land register, a report is posted on the building, owners are notified via e-Government and it is announced at the neighbourhood office for fifteen days. Owners have fifteen days to object; objections are reviewed by a technical board of university academics and officials of the Ministry and the Presidency.

Owners’ decision and land shares

Reconstruction, flat-for-land arrangements, revenue sharing and other ways of using the plot of a risky building are decided by a simple majority of co-owners in proportion to their shares. The decision and the terms of the agreement are notified to owners who did not join the decision through a notary or by a fifteen-day announcement at the neighbourhood office. If the offer is not accepted within fifteen days of this notice, the land share of the dissenting owner is sold by auction to the agreeing co-owners for no less than its market value.

Eviction, demolition and assistance

Owners are given a period of no more than ninety days to have a risky building demolished. If it is not demolished in that time, eviction and demolition are carried out by the administration and the costs are collected from the owners in proportion to their shares. Owners and tenants of buildings vacated by agreement may receive temporary housing or business premises or rent assistance; the conditions and amounts depend on the rules in force on the date of application. Certain transactions under the law are exempt from notary and land registry fees and stamp duty.

Contractor and flat-for-land agreement

A flat-for-land construction contract should clearly set out the allocation of units, the delivery period, guarantees, who bears rent assistance and the consequences of delay. If, for reasons attributable to the contractor, construction does not start within one year of the decision or the works stop for at least six months, the owners may decide by a simple majority in proportion to their shares to terminate the contract and apply to the Presidency.

Objections and court actions

Administrative acts in this field may be challenged before the administrative courts within thirty days of notification. A claim that the sale price of a land share was calculated too low may also be brought before the courts. Contract disputes between owners and the contractor fall within the jurisdiction of the civil courts.

Before the meeting

Bringing the title deed record, the risky building assessment report and notification documents, any decision of the owners’ meeting, the contract or draft contract with the contractor and related correspondence makes the assessment easier.